API 653 Practice Questions (Free, With Explanations)

Take the free API 653 diagnostic: 25 questions, about 40 minutes, your score by topic and where to start.

By Sandeep Bandyopadhyay, Engineer and founder of CertCrafter · PMP, MBA Updated

TL;DR

Three free API 653 practice questions sit further down this page, each with the full answer and explanation. They follow the exam's own shape: 110 closed-book questions in 2 hours 45 minutes, then 60 open-book questions in 3 hours 45 minutes, 170 in total and 140 scored. Passing is a scaled 400 on a 200-500 scale. Windows from March 2027 use the API 650 14th Edition sheet.

Original questions, not exam dumps. Every CertCrafter question is written from the published body of knowledge and the referenced codes. None is copied from a live exam, and CertCrafter is independent: not affiliated with or endorsed by any awarding body.

A row of white oil storage tanks with external stairways at a terminal on Halul Island
Photo: Oil storage tanks on Halul Island by Alex Sergeev (www.asergeev.com) (Wikimedia Commons), CC BY-SA 3.0, via Wikimedia Commons.

Well-prepared API 653 candidates still lose marks to the exam day itself: an untimed practice habit, a tabbed paper copy the test center will not allow, or practice written to an API 650 edition that no longer applies.

What do these free API 653 practice questions test?

The three questions further down this page are original, written from the published body of knowledge, and each carries a full explanation you can open once you have committed to an answer. They come from the same free sample that backs the scored API 653 quiz.

They touch three of the five body of knowledge sections, and all three are closed-book items. That matters more than the topic labels. A closed-book item has to be answerable from what you carry in your head: which corrosion rate governs, which interval rule applies. An open-book item is built around locating the right requirement in the right document.

None of the questions asks you to recite anything. Each one puts you in front of a decision an inspector has to make, such as electrodes left out overnight, because the exam tests judgment around the codes, not recall of them.

Video: API 653 — Settlement, thickness, interval — one calculation, one number. API 653 — Settlement, thickness, interval — one calculation, one number. Watch on YouTube · CertCrafter
Image: video thumbnail, source: CertCrafter on YouTube (@certcrafters).

How is the API 653 exam structured?

API puts the exam day at 7.5 hours at the test center: a short tutorial session, 2 hours 45 minutes for the closed-book portion, a 45-minute lunch break, then 3 hours 45 minutes for the open-book portion.

There are 170 questions, 110 closed-book and 60 open-book. Only 140 are scored; the remaining 30 are unscored pretest items, and they are not flagged, so answer every question. That works out to roughly 1.5 minutes per closed-book question and about 3.75 minutes per open-book question. Candidates who have only practiced untimed tend to overspend early and then rush the part of the exam that carries the most reading. Once you submit the closed-book section, you cannot go back into it.

The exam runs in person at a Prometric test center, and the reference documents appear as PDFs on your screen during the open-book portion only. If you have been studying with a tabbed paper copy of API 650, rehearse on screen.

The API 653 exam day in order: 110 closed-book questions in 2 hours 45 minutes, a 45-minute break, 60 open-book questions in 3 hours 45 minutes, pass at a scaled 400
The exam day, in order. Illustration: CertCrafter, from API 653 certification page.

What score do you need to pass API 653?

A scaled 400 on a 200-500 scale. API publishes no raw percentage and no per-form cut score, so any site telling you that you need 70 or 80 percent is guessing or confusing the exam with the recertification webquiz. The most recent published result at the time of writing is the November 2025 administration: 503 candidates at 60.8 percent.

Welded steel storage tanks under construction at a fuel depot, with dome roofs and a fenced site gate
Photo: Puma fuel depot under construction, Kwinana Beach, March 2020 by Calistemon (Wikimedia Commons), CC BY-SA 4.0, via Wikimedia Commons.

Which code editions apply to the API 653 exam in 2027?

Windows from March 2027 onward run on the March 2027 effectivity sheet, which lists API 650 in its 14th Edition of August 2025 and ASME BPVC Sections V and IX in their 2025 Editions.

The November 2026 window is the last one on the older sheet, which still used API 650 13th Edition and ASME BPVC 2023, and its application deadline of September 4, 2026 has passed. A practice set written against API 650 13th Edition will quietly point you at superseded table values and requirements.

Timeline of API 653 exam windows: the November 2026 window, whose September 4, 2026 deadline has passed, uses the March 2026 sheet with API 650 13th Edition and ASME BPVC 2023; the March, July and November 2027 windows use the March 2027 sheet with API 650 14th Edition and ASME BPVC Sections V and IX 2025
Which effectivity sheet applies to each window. Illustration: CertCrafter, from API 653 Aboveground Storage Tank Inspector certification page.

Only the specific sections of publications listed on that sheet are available to you during the open-book portion.

When are the API 653 exam dates and application deadlines?

API 653 runs in March, July and November. For 2027:

Exam window Application deadline
March 12 - April 2, 2027 January 07, 2027
July 09 - 30, 2027 May 06, 2027
November 05 - 26, 2027 September 02, 2027

The deadlines sit roughly two months ahead of each window. Initial certification for 2027 is $890 for API members and $1,140 for non-members, and a late application costs a further $200. Full detail is on API’s certification page and the schedules and fees page.

Which formulas does the exam give you, and which tables must you know?

Fewer than candidates fear. The body of knowledge states that the corrosion rate, remaining life, remaining corrosion allowance, maximum fill height and bottom plate formulas will be provided.

What is not provided is the judgment, such as which thickness belongs in which variable. The API 653 tables marked with an asterisk in the body of knowledge may be tested without document access, so those have to be carried in your head.

Why do API 510 and API 570 notes mislead you here?

Because the referenced publications are genuinely different. The construction standard for API 653 is API 650, and the inspection practices reference is API RP 575. ASME Section VIII is not a referenced publication for this exam at all, and neither is API RP 2350.

There is also no rerating in API 653. A tank’s maximum fill height and maximum allowable liquid level get re-evaluated; an MAWP does not get rerated. If your notes talk about rerating a tank, they came from a pressure vessel syllabus.

How should you use three free questions?

Not as a readiness test. What three questions can do is expose a habit. Read every explanation, including on the questions you answered correctly, because a right answer reached by the wrong route will fail you on a differently worded item. When you miss one, log it twice: once by section, and once by what went wrong. A pattern in the second column tells you what to study next.

Only full-length practice to the real rhythm measures readiness. The API 653 practice test bundle has six complete tests in real exam order. The API 653 guide has the full fact sheet and a phased study plan.

What these questions will not do

None of them is copied from a live exam, and none cites a clause, table or figure number, so you learn the requirement rather than a citation. No practice set replaces the codes the exam is drawn from.

The API 653 Complete Exam Kit works many more of these inspector decisions under timed conditions, closed book and open book, with every answer explained.

Try these free questions

  1. A thickness table in the governing standard is published only in US customary units, while the field readings on TK-1204 were logged in millimetres. How should the evaluation be carried out?

    1. Round the millimetre readings to the nearest sixteenth of an inch first, since the table is built on fractional inch steps and interpolation is not permitted.
    2. Convert the readings to the units of the published table and keep the whole evaluation in that one system, since the two unit sets are independent and must not be mixed.
    3. Apply the table as printed to the millimetre values, because the numerical steps in each system are close enough for an acceptance decision.
    4. Treat the absence of an SI table as a gap and use the corresponding SI table from the construction standard in its place rather than converting any of the field data.
    Show the answer and explanation

    Answer: B. API 653 and API 650 publish US customary and SI values as parallel but independent sets, and the SI figures are rounded rather than exact conversions of their customary counterparts. Mixing a millimetre measurement with an inch table therefore produces an evaluation that belongs to neither system, and the correct handling is to convert the measurements into the units of the table being used and complete the whole calculation in that system. Both unit systems are examinable, and some tables exist in only one of them, so this situation is routine rather than exceptional. Option one adds rounding to fractions, which throws away real precision in the readings and has no basis in the standard. Option three reads inch values against millimetre numbers, an error of more than a factor of twenty five that would accept a badly thinned plate. Option four substitutes a table from a different context instead of doing the conversion the situation actually calls for.

  2. Work planned on TK-3301 involves cutting in a new NPS 12 shell nozzle in course 1 and replacing a corroded 4 ft by 4 ft area of sketch plate with new plate of the same thickness. How should the two jobs be classified?

    1. Both are repairs, because neither one changes the height or the diameter of the tank.
    2. The new nozzle is an alteration and the sketch plate replacement is a repair.
    3. Both are alterations, because both involve cutting and welding on material that retains product.
    4. Both are reconstruction, because shell and bottom material are being removed and replaced.
    Show the answer and explanation

    Answer: B. API 653 separates the two terms by what the work does to the tank. A repair restores or maintains the tank in a condition suitable for safe operation, and replacing a corroded area of sketch plate with new plate of the same thickness does exactly that. An alteration is work that changes the physical dimensions or the configuration of the tank, and cutting a new NPS 12 penetration into course 1 changes the configuration of the shell, so it is an alteration and carries the design, reinforcement and examination requirements that go with it. Option 1 reads alteration as limited to changes in height or diameter, which is narrower than the definition. Option 3 assumes any cutting and welding makes work an alteration, which would sweep in every weld repair ever made. Option 4 misuses reconstruction, a term API 653 reserves for work involving dismantling and reassembly of a tank, usually after relocation, not for in place repair of a tank that stays where it is.

  3. A canister of E7018 electrodes sat open on the scaffold overnight beside T-305 during rain, and the welder wants to run them out in the morning on a shell insert repair. What should the inspector direct?

    1. Let the welder use them after a visual check for cracked or flaking coating, since moisture affects only the appearance of the flux and not the deposited weld metal.
    2. Let the welder use them on fillet and attachment welds only, keeping them off the full penetration seams where weld soundness matters most.
    3. Have the electrodes dried with a torch at the joint immediately before striking the arc, which drives off surface moisture and restores the coating.
    4. Take them out of service for rebaking or disposal within the manufacturer's exposure limits, because a low hydrogen coating that has absorbed moisture invites porosity and hydrogen cracking.
    Show the answer and explanation

    Answer: D. The whole point of a low hydrogen electrode is a coating that carries very little moisture, and that property is lost once the coating has been exposed to a wet atmosphere beyond the permitted exposure time. Moisture dissociates in the arc and delivers hydrogen into the weld pool and the heat affected zone, where it produces porosity and, in a restrained shell insert, delayed cracking that may not appear until after the examination is finished. Exposed electrodes must therefore go back for rebaking within the limits the manufacturer and the site procedure allow, or be scrapped. The first option treats moisture pickup as cosmetic. The second confines suspect consumables to fillet welds, as though an attachment weld cracking into the shell were acceptable. The third substitutes a torch for controlled rebaking, which heats the surface without driving moisture from the depth of the coating and can damage the flux while giving false confidence.

Take the full free 10-question sample with scoring →

Frequently asked questions

How many free API 653 practice questions are on this page?

Three, each with its options and a full explanation behind a toggle. All three are closed-book items, and between them they touch three of the five sections of the body of knowledge. A scored ten-question sample sits on the free quiz page, and the paid bundle holds 1,020 questions across six full-length tests.

Are these questions written to the 2027 code editions?

Yes. They follow the March 2027 effectivity sheet, which lists API 650 in its 14th Edition of August 2025 and ASME BPVC Sections V and IX in their 2025 Editions. Material written for the November 2026 window used API 650 13th Edition and ASME BPVC 2023, so older practice sets can point you at superseded requirements.

Can free practice questions tell you whether you are ready?

Three questions cannot. They tell you whether a particular habit is sound, such as reading an interval rule correctly or spotting which thickness belongs in which variable. Readiness shows up only in full 170-question runs timed to the real 2 hours 45 minutes closed-book and 3 hours 45 minutes open-book rhythm, scored by section.

Official sources

  1. API 653 Aboveground Storage Tank Inspector certification page — accessed 6 October 2026
  2. API ICP Schedules & Fees — accessed 6 October 2026

Exam rules change. Check the awarding body's official page before you apply. CertCrafter is independent and is not affiliated with or endorsed by any awarding body.

Was this helpful?

Comments

    Comments are read by a person before they appear. How we moderate.