My 4 engineering books go FREE on Kindle Fri 6 – Tue 10 Nov (PT). See the books → FREE on Kindle now: all 4 engineering books, until Tue 10 Nov 11:59 pm PT. Ends in . Grab yours → My 4 books: FREE on Kindle Fri 6 – Tue 10 Nov (PT). See → FREE on Kindle now: 4 books, left Grab yours →

PMP 2026 Practice Questions, Set 2 (Free)

By Sandeep Bandyopadhyay, Senior aerospace engineer · PMP, MBA, Six Sigma

TL;DR

This second free set of PMP 2026 questions is about authority: a blocker the team cannot clear, a conflict a governance body owns, and a sponsor who is away. PMI's July 2026 outline puts governance escalation, impediments and compliance in Business Environment, 26% of the exam. Work out who owns the decision before you read the options.

Original questions, not exam dumps. Every CertCrafter question is written from the published body of knowledge and the referenced codes. None is copied from a live exam, and CertCrafter is independent: not affiliated with or endorsed by any awarding body.

Many PMP candidates know what to do about a blocker and still lose the point. The stem asked who should deal with it, and they answered as if it were their own.

Attendees at an annual planning meeting reviewing the plan together
Photo: Annual plan meeting Wikimedia Sudan 15 by Hassan Hassoon (Wikimedia Commons), CC BY-SA 4.0, via Wikimedia Commons.

Why do so many PMP questions turn on who decides?

Because the outline tests it by name. In the Business Environment domain, which PMI’s July 2026 outline weights at 26%, the first task is to define and establish project governance, and one enabler is to outline governance escalation paths and thresholds. Another task is to remove impediments and manage issues.

Read those two together and you have the shape of a whole family of questions. A blocker appears. The stem tells you, in one detail, who owns it. Your job is to notice that detail before you choose.

Video: PMP Risk Management Explained: Register, Responses, Reserves and Risk vs Issue (2026 Exam) PMP Risk Management Explained: Register, Responses, Reserves and Risk vs Issue (2026 Exam) Watch on YouTube · CertCrafter
Image: video thumbnail, source: CertCrafter on YouTube (@certcrafters).

The channel’s video on risk management, register and reserves covers the neighboring skill, spotting the moment a risk becomes an issue, which the same task lists as an enabler.

What does the outline say about blockers?

The task is called Remove impediments and manage issues, and its enablers read like a short procedure. Evaluate the impact. Prioritize and highlight. Determine and apply an intervention strategy. Reassess continually. The last two enablers add recognizing when a risk becomes an issue, and collaborating with relevant stakeholders on an approach to resolve it.

Four steps from the PMP outline task Remove impediments and manage issues: evaluate the impact, prioritize and highlight, determine and apply an intervention strategy, reassess continually
The first four enablers of the impediments task. Illustration: CertCrafter, from PMP Examination Content Outline, July 2026 (PMI).

Notice what the list does not say. It does not say the project manager clears every blocker personally. An intervention strategy can be a decision, a request, or a handover to the person with the remit.

How do you tell whose problem a blocker is?

On a real project you ask three things in order. Can the team clear it with its own effort? If not, is the decision inside the project’s stated authority? If not, who does the organization say owns it?

Flow chart: a blocker appears, can the team clear it, if yes apply the intervention, if no check whose remit it is, inside the project decide and record it, outside the project escalate with a date attached
Illustration: CertCrafter, from the PMP Examination Content Outline, July 2026. Illustration: CertCrafter, from PMP Examination Content Outline, July 2026 (PMI).

The trap sits in the last box. Teams are good at logging a blocker, raising it at stand-ups and building a workaround. None of that moves it. A blocker that someone outside the project owns needs a request to that person, with a date by which you expect an answer, and a plan for what happens if the date passes.

Which three free questions should you try first?

Cover the options and find the sentence that says who owns the problem. Then choose.

The first is a regulated device release where a test environment lost its link to reference data. The team did everything a team can do. Ask what a team cannot do, and when it should have stopped trying.

The second is an AI assistant for bank staff where two senior heads disagree about what the screen shows. The stem names a committee and its remit. Check whether that remit covers the disagreement, and do not settle for the answer that merely sounds fair.

The third is an iteration where a sign-off role went empty after a restructuring. Count what is blocked and what is not. The stem also tells you who is on leave and who has a stated response target.

What do these three questions test?

Scenario ECO task it draws on
Environment owned by another function Remove impediments and manage issues
Two executives and a governance committee Align stakeholder expectations, Manage conflicts
Empty sign-off role mid-iteration Remove impediments and manage issues

Two of the three sit in the same task. That is typical: the exam returns to the same idea in different clothes, and the clothes are what trip people up.

The PMP Complete Exam Kit works more of these under timed conditions, with every answer explained.

A second view of the planning meeting, with attendees at the table
Photo: Annual plan meeting Wikimedia Sudan 14 by Hassan Hassoon (Wikimedia Commons), CC BY-SA 4.0, via Wikimedia Commons.

How does this show up on a real project?

Picture a vendor-owned test rig that goes down. The team can write a better workaround every week. Only the vendor’s account manager, or someone above both parties, can get the rig fixed. Experienced project managers escalate early, because they know each week of workaround is a week of accepted risk that nobody with authority has seen.

Governance disputes work the same way. When a model, a safety rule or a regulation is involved, the organization has usually named a body to rule on it. A sponsor can set priorities, but not outside that body’s remit. A project manager who lets two executives trade a compromise on a controlled item creates rework the committee will order later.

Restructurings add a third version. Roles vanish and sign-offs go with them. The useful move is rarely to stop everything. It is to keep unblocked work moving, name the gap to whoever owns the restructuring, and attach a date.

What mistakes do these questions catch?

Three patterns, each with a different fix.

Escalation too late. You tracked a blocker for weeks. The cure is to set a threshold when the blocker appears, for example a number of days, and treat crossing it as the trigger.

Escalation to the wrong person. The sponsor funds the work, so the sponsor decides everything. Read the stem for a named body or role with a remit, and send the matter there.

Doing nothing visible. The team is blocked, so you wait. Look for ready work that does not touch the blocker and pull it in.

Log each miss under one of those labels. After a dozen questions the label that keeps returning tells you which habit to rehearse.

What should you do after the free questions?

Try Set 1 of the free questions if you skipped it, take the free sample quiz, and read how the People domain is tested and which common PMP mistakes cost the most points. The PMP 2026 certification page, the practice test bundle and the PMP guides hub have the rest.

Try these free questions

  1. An insurer is being restructured, and the legal review function has been folded into a new risk and compliance group. Halfway through a two week iteration, the reviewer who normally signs off customer wording is no longer in post and nobody has been named in her place. Three of the eight stories the team committed to need that sign off before they can be called done. Five stories carry no legal dependency, and the refined backlog holds several ready items of similar size. The transition lead for the restructuring has a published mailbox and a stated two day response target. The team's morale has held up well and the sponsor is on leave for a week. What should the project manager do next?

    1. Keep the three stories open and have the whole team assist the five remaining stories through to completion, accepting that the iteration goal will be only partly met.
    2. Split the three stories so that the parts needing no legal sign off can be marked complete inside this iteration.
    3. Contact the sponsor on leave and ask for the previous reviewer to be temporarily reinstated until the new compliance group is staffed.
    4. Pull ready items with no legal dependency into the iteration to protect the goal, and put the unnamed reviewer to the transition lead with a resolution date.
    Show the answer and explanation

    Answer: D. Two facts have to be held together: the blocking condition sits outside the team and will not clear on the team's timescale, and there is ready work that does not touch it. That combination makes reprioritising the right move rather than an evasion. Pulling in ready items with no legal dependency keeps the iteration producing value while the three stories wait, and naming the missing reviewer to the transition lead, with a date attached, puts the impediment in front of the only person who can resolve it during a restructuring. The date matters, because an impediment raised without one drifts. Keeping the three stories open and piling the team onto the remaining five sounds like focus, but five stories will not absorb eight people, and the iteration ends with idle time and a missed goal for no gain. Splitting the stories so the unreviewed parts can be called complete is the most dangerous option because it looks agile: it breaches the definition of done, and customer wording that has not been reviewed sitting in a done column is how unreviewed wording reaches customers. Reaching the sponsor on leave to reinstate the old reviewer skips the person accountable for the transition and asks for a decision the restructuring has already taken. Escalation would be right if the transition lead missed the stated date. ECO Domain III, Business Environment, task 'Remove impediments and manage issues'; PMBOK Guide Eighth Edition, Resources Performance Domain.

  2. Penrith Diagnostics shipped a firmware release that mis-reported one analyser reading, and the escape was caught by a hospital customer rather than by the project team. During the recovery review the team lead recalls that six weeks before release the test environment lost its link to the regulated reference data set, so the full verification suite could not be run. The team raised this in three consecutive standups, logged it, and worked around it by testing against a sampled copy. The environment is owned by a separate infrastructure function reporting to a different director, and nobody on the project could compel a fix. The project manager tracked the item as a team impediment for the whole six weeks and kept the workaround in place. The delivery date, fixed by a regulatory submission window, never moved. What did the project manager most likely fail to do?

    1. Rescored the release risk at each sprint boundary and raised its probability rating in the register as the workaround persisted
    2. Asked the infrastructure engineers to slot the environment rebuild into their own backlog refinement
    3. Added a compensating step so that results from the sampled data were independently reviewed before release sign-off
    4. Handed the blocked environment to the body with authority over both functions once the team's own attempts had failed
    Show the answer and explanation

    Answer: D. This item turns on the boundary of the project manager's authority, and the settling detail is that the blocked environment belonged to a function outside the project reporting to a different director. An impediment the team cannot clear by its own effort has stopped being a team impediment, whatever the standup notes call it. The keyed answer is that the blockage needed to go to a body with authority over both areas as soon as the team's own approaches had failed, and it needed to go there in week one rather than week six. Escalation here is not passing the problem along; it is the only route to a decision the project manager was never able to make. Rescoring the risk each sprint is tidy record keeping that changes nothing, because a rising score with no owner able to act is simply a documented failure in progress. Asking the infrastructure engineers to squeeze the rebuild into their own refinement is the collaborative move candidates are trained to prefer, and it is roughly what the team spent six weeks doing; it fails because the priority call belonged to their director, not to them. Independent review of sampled results is the most seductive option because it is technically sensible, and it would be a reasonable holding measure for a week or two while an escalation ran. Used instead of escalation on a regulated device, it accepts a verification gap rather than removing it, which is how the escape reached a patient. ECO Domain III, Business Environment, task 'Remove impediments and manage issues'; PMBOK Guide Eighth Edition, Governance Performance Domain and the Be an Accountable Leader principle.

  3. Ardent Bank is building an AI assistant that suggests next actions to branch staff during customer conversations. The head of retail operations wants a single recommended action displayed, arguing that staff freeze when given choices and that handling time will suffer. The head of compliance insists every suggestion show the evidence behind it and an explicit option to decline, which the model team says will roughly double response time but is technically straightforward. The bank operates a model risk governance committee, chaired by the chief risk officer, whose remit covers the behaviour of any model influencing customer outcomes. The requirements baseline is due in two weeks, the pilot branches are already selected, and the sponsor, the retail director, has told you to settle the argument quickly. What should the project manager do?

    1. Facilitate a workshop between the two heads, help them reach a position both can support, and baseline whichever requirement emerges from that discussion.
    2. Take the conflict to the model risk governance committee, since the transparency requirement sits inside its remit, and baseline what it confirms.
    3. Baseline the compliance requirement, on the basis that a regulatory requirement will always outrank an operational preference about staff handling time in a bank.
    4. Ask the sponsor to choose between the two positions, since the retail director funds the project and is entitled to set its priorities before the baseline is fixed.
    Show the answer and explanation

    Answer: B. Both heads are senior and both arguments are reasonable, which is exactly why the answer is not about who is more persuasive. The stem names a model risk governance committee chaired by the chief risk officer whose remit covers the behaviour of any model influencing customer outcomes, and whether an AI assistant shows its evidence and allows a decline is model behaviour affecting customers. That places the decision outside both business heads and outside the sponsor. Option 2 takes it where it belongs and then baselines the confirmed requirement, which also gives the project a defensible record when the assistant is later reviewed. Option 1 is the collaborative answer and it is the trap. Two executives agreeing between themselves cannot waive a requirement that a governance body owns, and a negotiated compromise on transparency would have to be unpicked later, after the baseline, at far greater cost. Option 3 reaches the outcome the committee may well confirm, but it gets there by applying a slogan instead of establishing authority, and it prejudges a body that might permit a single recommendation with evidence available on request. A correct answer by accident is still a governance failure. Option 4 is the escalation reflex pointed at the wrong person; the sponsor funds the work and can set priorities within his authority, and model risk is not within it. ECO Domain I, People, tasks 'Align stakeholder expectations' and 'Manage conflicts'; PMBOK Guide Eighth Edition, Governance and Stakeholders Performance Domains.

Take the full free 10-question sample with scoring →

Frequently asked questions

How many tasks are in the 2026 PMP outline?

The outline lists 26 tasks across the three domains: 8 in People, 10 in Process and 8 in Business Environment. Every exam addresses all tasks of a domain.

Where do impediments sit in the 2026 PMP exam?

In the Business Environment domain, under the task Remove impediments and manage issues. Its enablers include evaluating impact, prioritizing and highlighting impediments, applying an intervention strategy and reassessing continually.

Are these free PMP questions different from Set 1?

Yes. Set 1 used one question from each domain to teach scenario reading. This set uses three questions that turn on authority and governance, so the habit you practice is asking who decides.

Official sources

  1. PMP Examination Content Outline, July 2026 (PMI) — accessed 6 November 2026

Exam rules change. Check the awarding body's official page before you apply. CertCrafter is independent and is not affiliated with or endorsed by any awarding body.

Was this helpful?

Comments

    Comments are read by a person before they appear. How we moderate.